national aquarium
‘...The greatest moment came when the main ocean tank was filled...'
CLIENT Napier City Council
CONTRACT PERIOD 18 months
DATE COMPLETED March 2002
APPROXIMATE COST $8.5m
PRINCIPAL CONSULTANT Architecture Warren & Mahoney
SKOPE OF WORK To refurbish and restrengthen the existing two storey circular Aquarium building and construction of a new 1800m2 building containing a 1,500,000 litre ocean tank, acrylic tunnel and travelator, service and retail areas and a research facility.
HIGHLIGHTS The project was built to tight tolerances due to the lead time on the imported acrylic panels requiring them to be ordered before the openings and rebates were formed and the special marine water tightness requirements meant stringent quality standards were required to be maintained. The cylindrical roof also created some challenges at shop drawing stage being effectively curved in three directions. The greatest moment came, however, when the main ocean tank was filled and we couldn’t find a leak.
For more information on this project or if you have a similar project please contact the team today!
|