countdown napier
‘...Keeping a large supermarket operational throughout a major refit...'
CLIENT General Distributors Ltd
CONTRACT PERIOD 8 months
DATE COMPLETED August 2004
APPROXIMATE COST $1.6m
PRINCIPAL CONSULTANTS Booth Sweetman Wolfe Ltd
SKOPE OF WORK Relocation and replacement of aisles and shelving, demolition and relocation of the bakery and upgrading of the produce, deli and fish departments; the construction of electrical, water and service ducts throughout and installation of new checkouts.
HIGHLIGHTS This project required stringent programming and staging throughout to accomodate numerous trade subcontractors and keep service departments operational without disruption or safety concerns for customers. Overcoming these challenges and achieving our completion dates were real highlights of this particular project.
For more information on this project or if you have a similar project please contact the team today!
|